DESIGN AND BUILD - KOMPLEKS PKNS SHAH ALAM

DESIGN AND BUILD

ROYALLEKOR SHAH ALAM.

DURATION: 4 WEEKS

PERSON IN CHARGE:
DESIGN : ANEP
MANAGEMENT : AAM
BILL OF QUANTITY : MEMER
DRAWINGS : AKRIMEE

SOFTWARE : AUTODESK REVIT

FIRST DESIGN 


SECOND DESIGN






THIRD DESIGN

CONSTRUCTION

1. clearance of the site area, checking for preparing a measured drawing.
2. Demolition start with ceiling and removing the wall tile.
3. Unexpected old wiring at ceiling area, the wall was not attached to the slab.
4. All old wire were removed. 
5. Clean up everything, touch-up on wall plaster.
6. Additional ceiling at upper slab area.
7. Painting work at slab surface and wall.
8. Additional cable tray and wiring job.
9. Final!